Many subcontractors get their submittals from the supply house: the distributor offers to “put the submittals together” and sends a stack of cut sheets. It feels like the job is done. Then the package comes back “Revise and Resubmit.” Here is why that happens and how to fix it.

What a supplier package is built to do

A distributor’s submittal package is designed to get its products approved. That is useful: the supplier knows its catalog, the model numbers and the lead times. But the supplier is not responsible for your contract, and usually does not read the project’s specification book. The package reflects what they sell, not what the architect specified.

What the reviewer is checking

The architect or engineer reviews each submittal against the specification section it belongs to. They are looking for the exact products, options, ratings, certifications and documents that section requires, and for anything that deviates from it.

Supplier packageSpec-compliant submittal
Organized by product line or orderOrganized by spec section, numbered the way Division 01 requires
Catalog pages with every option shownExact model, size, options and accessories highlighted
Brands the supplier stocksBasis-of-design or listed manufacturers, or a documented substitution
Product data onlyEverything Part 1 requires: product data, shop drawings, certificates, warranties, samples
No deviations listedEvery deviation from the spec stated up front, with the reason
No contractor reviewYour review and certification that it was checked against the documents

The most common gaps

  • A fixture submitted without its carrier, trim, valve or drain, so the assembly can’t be approved.
  • Flow rates, pressure ratings or efficiency values that differ from the spec.
  • A different manufacturer than specified, with no substitution request or comparison.
  • Missing certifications the spec calls for, such as lead-free, listing or Buy America documents.
  • Warranty terms shorter than specified.
  • No transmittal or contractor review stamp.

How to use a supplier package the right way

  1. Ask the supplier for its product list and data sheets early.
  2. Pull the spec section for each product and read Part 1 (submittals) and Part 2 (products).
  3. Check each product against Part 2: model, options, ratings, finishes.
  4. Mark up the data sheets so the reviewer sees the exact selections.
  5. Add what the supplier didn’t include: certificates, warranties, shop drawings, samples.
  6. List deviations on the transmittal, then review and stamp it before it goes to the general contractor.

Who is responsible?

Under most construction contracts, the contractor submitting the package is responsible for reviewing it and confirming it meets the contract documents. A supplier can help, but the responsibility stays with you.

Short on time? We do exactly this: take your supplier’s selections, check every item against the spec and deliver packages ready to submit. See submittal services for small subcontractors, or make your own contractor review stamp with our free review stamp maker.

Frequently asked questions

Can my supplier prepare my submittals?

A supplier can provide product data and help with selections, but its package is built around the products it sells, not your project’s specification. You are still responsible for making sure each submittal meets the contract documents.

Why was my supplier’s submittal rejected?

The most common reasons are missing items the spec requires, products or ratings that differ from the spec, unhighlighted catalog pages, and no list of deviations or contractor review.

Do I have to review submittals before sending them?

Most specifications require the contractor to review, approve and stamp submittals before they go to the architect or engineer.

Can you fix a supplier package for us?

Yes. SubmittalShop checks supplier selections against the spec, fills the gaps and delivers complete packages at a flat price.

Send us your spec book. Get a flat quote in 48–72 hours.

No account, no software and no retainer. Tell us the sections you need and we price exactly that.

Get a Flat-Rate Quote