Every submittal comes back with a stamp. The wording varies between firms, but the outcomes are almost always the same handful. Misreading one can mean ordering material you can't install, or sitting idle on something you were cleared to buy. Here's what each stamp means and what to do next.

StampMeaningCan you proceed?
Approved / No Exceptions TakenConforms with the design intent as submittedYes
Approved as Noted / Make Corrections NotedAcceptable once the reviewer's notes are appliedYes, incorporating every note
Revise and ResubmitCorrections or missing information needed before approvalNo, not until a revision is approved
Rejected / Not ApprovedDoesn't meet the contract documentsNo; a different product or approach is needed
Not Reviewed / Not RequiredThe reviewer didn't review it, often because it wasn't requestedDoesn't grant approval; check what the spec requires
Received for Record / Information OnlyAn informational submittal was received and filedYes, if no approval was required

Approved as Noted: read every note

This is the most common result and the easiest to mishandle. The notes become part of what's approved, so pass them to your purchasing and field teams. If a note changes a model, finish or accessory, confirm the change with your supplier before ordering. Some reviewers also ask for a corrected copy "for record," which doesn't hold up procurement but should still be sent.

Revise and Resubmit: fix it, then answer every comment

Correct each item, add what's missing, increase the revision number (for example 224213-001.0 to 001.1), and include a short written response to each comment. Cloud changes on drawings. Reviewers process a clear, responsive resubmittal much faster than a fresh package they have to compare line by line.

Rejected: change direction

A rejection usually means the product doesn't meet a requirement, an unapproved substitution was submitted, or the package was too incomplete to review. Re-read the spec's Part 2 and the reviewer's reason, select a compliant product, and if you believe the reviewer misread the documents, ask in an RFI rather than resubmitting the same thing. Our article on common rejection reasons covers the patterns.

Approval isn't a change order

Most contracts say a submittal approval doesn't authorize changes to the contract sum or time, even when a reviewer's note adds scope. If a note adds cost, raise it with the GC as a change before you do the work.

Track every response

Record the stamp, date and next action for every package in your submittal log. Approved submittals also feed your closeout package later; see our guide to closeout submittals and O&M manuals.

Got a "Revise and Resubmit" sitting on your desk?

Send us the returned submittal and the comments. We'll fix every item and write the responses for the resubmittal.

Get a Flat-Rate Quote in 48–72h

Frequently asked questions

Can I order material on an 'Approved as Noted' submittal?

Usually yes, as long as you incorporate every note. Check whether the notes require you to resubmit anything first; some reviewers combine 'Approved as Noted' with 'Resubmit for Record' or a request for a specific item.

What's the difference between 'Revise and Resubmit' and 'Rejected'?

'Revise and Resubmit' means the approach can work but the submittal needs corrections or missing information. 'Rejected' means the product or approach doesn't meet the documents and you need a different solution.

Does the GC stamp count as approval?

No. The general contractor's stamp shows they reviewed and forwarded the submittal. Approval comes from the architect or engineer's review stamp, unless the contract says otherwise.

Why do reviewers use different wording?

Each firm uses its own stamp. The wording varies, but almost every stamp maps to the same few outcomes described in this guide. When in doubt, ask the reviewer before ordering material.