The Shop Drawing Submittal Process, From Drafting to Approval

BY SUBMITTALSHOP TEAM
•
UPDATED OCTOBER 2, 2026
•
7 MIN READ

Shop drawings show how you will fabricate and install your work: exact dimensions, connections, materials and coordination with everything around it. They move through the same review chain as product data but take longer to prepare and review. Here's how the process works and where it usually stalls.

The review chain

StepWhoWhat they check
1. PrepareSubcontractor or detailerField dimensions, spec requirements, coordination with other trades
2. GC reviewGeneral contractorCompleteness, coordination, schedule; stamps and forwards
3. Design reviewArchitect and/or engineer of recordGeneral conformance with the design intent and contract documents
4. ReturnBack down the chainReview stamp and comments; approve, revise or reject

What a good shop drawing includes

  • A title block with project, spec section, sheet number, submittal number and revision
  • Plans, elevations, sections and details at scales the reviewer can read
  • Dimensions tied to building grid lines and verified field conditions
  • Materials, sizes, gauges, finishes and connections called out explicitly
  • Interfaces with adjacent work: structure, other trades, rated assemblies
  • Clouded and tagged changes on every revision

Delegated design: when an engineer's seal is required

Some specs make the contractor responsible for designing part of the work, such as steel connections, cold-formed framing, stairs and railings, curtain wall anchorage, or pipe and duct hanger systems. These "delegated design" submittals need calculations and drawings sealed by a professional engineer licensed in the project's state. Identify them early in the spec, because finding and scheduling an engineer can take longer than the drafting.

Where the process stalls

  • Dimensions that don't match the field. Verify before drafting, not after.
  • No coordination with other trades. Conflicts found in review turn into resubmittals.
  • Missing companion product data. Reviewers often won't approve drawings without the data for the products shown on them.
  • Unanswered questions drawn as guesses. Send an RFI instead.
  • Revisions with no clouds or responses. The reviewer starts from scratch, and the clock restarts.

Reading the stamp

"Approved as Noted" lets you proceed with the reviewer's corrections; "Revise and Resubmit" means you can't proceed until a revised set is approved. Our guide to submittal review stamps covers each response and what to do next. Track every cycle in a submittal log so the schedule impact is visible.

Need shop drawings drafted?

We draft trade shop drawings and assemble the companion product data, for mechanical, plumbing, openings and more.

Get a Flat-Rate Quote in 48–72h

Frequently asked questions

How long does shop drawing review take?

The contract usually sets it, commonly 10 to 14 working days for the design team after the GC forwards the submittal, plus the GC's own review time. Check Division 01 and the general conditions, and plan long-lead items around the full cycle including a possible resubmittal.

Does approval of shop drawings mean the design team accepts responsibility?

Generally no. Most contracts state that review is only for general conformance with the design intent, and the contractor remains responsible for dimensions, quantities, fabrication methods and coordination. Read the review stamp and your contract's language.

What is delegated design?

Work the specification makes the contractor responsible for designing, such as connections, stairs, curtain wall anchorage or hanger systems. Those submittals typically need calculations and drawings sealed by a professional engineer licensed in the project's state.

Can we start fabrication before shop drawings are approved?

Usually not without risk. Most contracts prohibit fabrication or installation of work requiring submittals until they are approved, and anything built earlier may have to be redone if the review changes it.