SubmittalShop
Submittal Basics

How to Build a Submittal Register from the Spec Book

BY SUBMITTALSHOP TEAM
•
UPDATED OCTOBER 3, 2026
•
7 MIN READ

A submittal register lists every submittal the contract requires, before work starts. Building it at the beginning of a job is the single best way to avoid late submittals, missed items and closeout surprises. Here is how to build one from the spec book.

Submittal register, submittal log or submittal schedule?

TermWhat it usually means
Submittal registerThe complete list of required submittals, built from the specifications at the start of the job.
Submittal logThe same list used to track status: dates sent and returned, revision and review action.
Submittal scheduleThe register with due dates tied to the construction schedule and lead times.

In practice they are often one spreadsheet. Our free submittal log template covers all three.

Step 1: Read Division 01 first

Section 01 33 00, Submittal Procedures, sets the rules: numbering, format, review times, number of copies and electronic submission requirements. Other Division 01 sections add closeout, sustainable design and quality requirements that create submittals of their own.

Step 2: Go through Part 1 of every section in your scope

Each specification section lists its submittals in Part 1, usually under “Action Submittals” and “Informational Submittals,” and sometimes “Closeout Submittals.” Create one line for each item.

Step 3: Use consistent columns

ColumnExample
Spec section & title22 42 13.16 Commercial Urinals
Submittal number224213-001
DescriptionUrinals, flush valves and carriers
TypeProduct data, shop drawing, sample, certificate, test report, O&M
Action or informationalAction (needs approval) or informational (for record)
Responsible partyYour company or supplier
Required by dateBased on schedule and lead time
StatusNot submitted, under review, approved, approved as noted, revise and resubmit

Step 4: Add dates that work backwards from the schedule

For each item, start with the date the material must be on site. Subtract the fabrication or delivery lead time, then the review time in Division 01 (often 10 to 15 working days, sometimes more), and time for one resubmittal. The result is the date the submittal must go out.

Step 5: Flag the long-lead and special items

  • Long-lead equipment such as switchgear, generators, elevators and custom air handlers
  • Delegated design items that need an engineer’s seal
  • Samples and mock-ups that need approval before production
  • LEED, Buy America or other special documentation

Federal projects: SD numbers

Federal specifications based on the UFGS use submittal descriptions SD-01 through SD-11, from preconstruction submittals and shop drawings to O&M data and closeout. Many agencies also require their own register form. Follow the agency format when it is required.

Keep it current

A register is only useful if it is updated each time a submittal goes out or comes back. Assign one person to keep it, and review it at every project meeting.

Frequently asked questions

What is a submittal register?

A submittal register is the complete list of submittals the contract requires, built from the specifications at the start of a project, and used to track every submittal through approval.

Who prepares the submittal register?

Usually the general contractor for the whole project, and each subcontractor for its own scope. Many specifications require the contractor to submit the register early in the project.

Where do I find the required submittals?

In Section 01 33 00 Submittal Procedures and in Part 1 of each specification section, under action, informational and closeout submittals.

Is there a free submittal register template?

Yes. The SubmittalShop submittal log template runs in your browser, prints and exports to CSV for Excel.

Send us your spec book. Get a flat quote in 48–72 hours.

No account, no software and no retainer. Tell us the sections you need and we price exactly that.

Get a Flat-Rate Quote